Development Phase One

The first phase of the development named 'St Godric's Walk was completed in February 2005. The first forty static vans were removed, landscaping and full services were introduced and all seventeen plots on phase one have been sold.

The outlined plan below shows the position of the first seventeen units. The plan shows the names of our residents or prospective residents as only ten of the seventeen plots already have lodges on site. Plans for the second phase can be seen on the phase two pages.

The following pictures track the progress of the work that was completed in March 2005 and show how the village was developed.

1st October 2004.

Work started, the old caravans were removed in preparation for the landscaping and foundation laying to begin.

Several large trees on the site had to be removed when it was discovered that they were hollow and unsafe.

End of the first week of work, large changes can already be seen.

 

Mr and Mrs Storey who were to become our first residents on the park in March 2005 were excited to see the work so far and couldn’t wait to move onto the park.

 

The contractors who have developed the park for us 'Metcalfe's' of Penrith did a first rate job! The plots took shape quickly and mains services were installed. Brian, Shaun the site manager, Andy the on site Supervisor and the gang, Bry, Jamie and Kim kept to a tight schedule although the weather didn’t help.

This picture shows the field drains being laid.

After another busy week mains services, gas, electricity, water and also telephone cables were laid.

After the ground was prepared the bases were marked out showing where each individual home will stand.

To provide firm foundations for the homes bases were reinforced with a steel framework.

The frames were then covered in concrete to form the platform onto which the homes will stand.

The reed bed was fully lined and prepared ready for the reeds, this ‘polishes' the water from the sewerage system after it comes from the treatment plant before it is returned to the stream and forms an important part of this eco-friendly system.

The large treatment plant was buried underground to complete the sewerage system which was supplied by Hutchinson's of Hexham. Hutchinson's provided a very professional service the standards of which far exceeded not only our own expectations but also the environmental guidelines.
http://www.hutchinson.co.uk/

 

 

Shaun as site manager and Andy on-site supervisor and the gang Bry, Jamie, Alan and Kim all worked hard throughout the development and were completing three bases a day.

A 'rock armour' wall was built to stop any movement of soil on the slopes around the park.


The hardcore road base was laid to give access to individual bases.

 

The gas tanks were positioned in the field behind the development to provide piped gas to all homes. These tanks were later buried for safety issues and also to enhance the look of the park.

The parking bays were the first areas to get the topcoat of tarmac followed by the roads themselves.

 

Is anyone else thinking Auf Wiedersehen Pet?

Shaun, Andy, Bry, Jamie, Alan and Kim from Metcalfe’s finished the ground work on phase one of the development in February 2005, a little behind schedule but to a very high standard which we were very pleased with.

Information showing the first homes arriving onto the park can be seen on the New Homes page.

Last updated - 16th February 2005

Back to development page.

For more information on the Park, our new development and availability of residential plots
please call Ann on 0191 3866528 or E-mail:
godricawatson@hotmail.com